BROWARD COLLEGE BUILDINGS 50 & 51

Project Description

BROWARD COLLEGE BUILDINGS 50 & 51

The project consists of the interior and exterior renovation and expansion of buildings 50 and 51. In order meet the needs of the end users an individual room analysis study was performed taking into consideration furniture layout, student occupancy, etc. The scope of work includes two computer labs, three presentation classrooms, ceramics instruction, art instruction, music/performance instruction, department reception area, workroom/lounge, conference room, associate's dean's office, facility and adjunct offices. 

Location: Coconut Creek, FL

Total Size: 39,200 SF

Construction Cost: $5,700,000.00

Owner: Broward College

Structural Engineers: Martinez Engineering Group

Mechanical, Electrical Engineers: Johnson, Levinson, Ragan, Davila, Inc

Civil Engineers: EAC Consulting Engineers